Archivo de la etiqueta: Egipto

Fabrication process of the goliath crane

The 60 ton capacity goliath crane shown in the pictures has 19.3 m span an 6 useful cantilever on one side of the crane. The hoisting equipment is made with an open winch system and the hook path is 35 m

The end customer is these two goliath cranes was a joint venture between two of the biggest well known Egyptian construction companies; Arab Contractos  and ORASCOM Construction Company.

 

Arab Contractors – ORASCOM JV has awarded SENER a contract within the roadway under the Suez Canal in Port Said (Egypt). This ambitious project of the Egyptian Government includes the design and construction of two tunnels under the Canal to connect the Sinai Peninsula with the rest of Egypt and thereby promote the future development of this peninsula.

In this project, SENER will carry out the conceptual, basic and detailed design of the tunnels, as well as civil works, associated electromechanical installations and intelligent transport communications (ITS). Specifically, the scope of work includes: two tunnels, excavated with TBM (Tunnel Boring Machine) technique, of approximately 2.80 km each; A road 9 km long; The emergency steps between tunnels, as well as the facilities associated with all these components (tunnels, road and steps), such as power and substations, lighting, fire protection and ventilation), ITS facilities such as variable signaling, Gauge control, communications, fire detection, CCTV (English acronym), and connection links with existing roads on both sides, including upper pass structures.

 

Estas grúa pórtico que tienen una luz de 19,3m. más 6m. de voladizo, están equipadas con un carro abierto de 60t. de capacidad que permite una elevación a 35m. de altura, con cable Veropro8 de 2×82,5m. y enrollador.

ArabContractors – ORASCOM ha adjudicado a SENER un contrato dentro del paso de carretera bajo el Canal de Suez en Port Said (Egipto). Este ambicioso proyecto del Gobierno egipcio comprende el diseño y construcción de dos túneles bajo el Canal para conectar la Península del Sinaí con el resto de Egipto y, de este modo, promover el desarrollo futuro de esta península.

En este proyecto, SENER va a llevar a cabo el diseño conceptual, básico y detallado de los túneles, así como las obras civiles, instalaciones electromecánicas y de comunicaciones de transporte inteligente (ITS en su acrónimo inglés) asociadas. Concretamente, el alcance de los trabajos abarca: dos túneles, excavados con técnica TBM (TunnelBoring Machine), de 2,80 km aproximadamente cada uno; una carretera de 9 km de longitud; los pasos de emergencia entre túneles, así como las instalaciones asociadas a todos estos componentes (túneles, carretera y pasos), como son la alimentación eléctrica y subestaciones, iluminación, protección contra incendio y ventilación), las instalaciones ITS como son la señalización variable, el control de gálibo, las comunicaciones, la detección de incendio, el circuito cerrado de televisión (CCTV en su acrónimo inglés), y los enlaces de conexión con las carreteras existentes a ambos lados, incluidas las estructuras de pasos superiores.

GH supplies bridge cranes for Egypt’s energy megaproject

On March 31, Siemens has reached financial close for the two combined cycle power plants, Burullus and New Capital, in Egypt.

Reaching the financial close is an important milestone towards building the two power plants- with a capacity of 4.8 Gigawatts (GW) each set to become the biggest gas-fired combined-cycle power plant complex around the world.

On March 9, the loan agreements of Burullus and New Capital were signed in Cairo– in the presence of the Egyptian Prime Minister, Sherif Ismail.

Covering major parts of Orascom Construction and Siemens´ scope, the financing of the two plants was provided by a consortium of international and regional banks. The credit facilities were largely covered by Export Credit Agencies.

For one of these projects, Burullus Combined Cycle Project, GH Cranes has supplied all required cranes based on:

  • Steam turbine building section

SMM01: 140/25 ton EOT Crane Span 31.1 m. Height of lift 19/22.8 m (4 UNITS) Cranes supplied in 2016 

SMM02:10 ton capacity EOT Crane. Span 11.4 m. Height of lift 14 m (4 UNITS) Cranes supplied in 2016 

  • Gas turbine building section

SMM01: 200/30/12.5 ton EOT Crane Span 16.4 m. Height of lift 20/21/18 m (4 UNITS) Cranes supplied in 2016 

SMM02:12.5 ton capacity EOT Crane. Span 15.3 m. Height of lift 12 m (8 UNITS) Cranes supplied in 2016

  • Travelling water screen and pumps gantry crane 25/20 ton with span 27.2 m and 16 m legs. Cranes to be supplied in 2017
  • One 5 ton capacity EOT Crane for workshops. Cranes to be supplied in 2017

All cranes were supplied in extremely challenging short periods thanks to the coordination in between different departments and production facilities of GH.

Source: www.power-technology.com
Photo Siemens

Grúa puente 200/30/12,5t para Orascom

Proceso de fabricación de carro abierto para grúa puente de 17m de luz y capacidad de elevación de 200t a 20m de altura.

_MG_3941_MG_3947La grúa cuenta con dos elevaciones auxiliares, la primera en polipasto fijo de patas GHG de 30t de capacidad y recorrido 23,7m y la segunda en polipasto fijo de patas GHE de 12,5t de capacidad y recorrido 15,8m.

_MG_3948 _MG_3944El gancho de la elevación principal lleva bloqueo de 4 posiciones a 90º.

20160408_114723 _MG_3954El pedido consta de dos puentes grúa de similares características que se entregarán al cliente Orascom Construcción y que se instalarán en El Cairo (Egipto).